In re SP Land Co., LLC, 2011 VT 104 (Johnson, J.) (Reiber, C.J., dissenting.)
The issue of whether a Rule 34(D) administrative amendment may be used to authorize a fifteen-lot subdivision absent positive findings on all Act 250 criteria is at the core of this case. Rule 34(D) states:
A district commission may authorize a district coordinator to amend a permit without notice or hearing when an amendment is necessary for record-keeping purposes or to provide authorization for minor revisions to permitted projects raising no likelihood of impacts under the criteria of the Act.
We hold that Rule 34(D) applies solely to the Act 250 land use permit issued after full substantive review of all ten statutory criteria under 10 V.S.A. § 6086(a) and cannot apply to findings of fact and conclusions of law on fewer than all of the Act 250 criteria for a master plan. The statute makes clear that the Legislature intended full review under all Act 250 criteria and subcriteria for just this kind of substantial subdivision.
Reiber, C.J., dissents because the issue the majority decides was not raised below in a timely and proper manner and therefore should not be reviewable on appeal. The question it addresses—whether an administrative amendment under Rule 34 requires an underlying Act 250 permit—was not raised with the trial court before the entry of judgment but only later in a Rule 59(e) motion to alter or amend.
No comments:
Post a Comment