Ferrisburgh Realty Investors v. Schumacher, 2010 VT 6 (Skoglund, J.)
Developer Ferrisburgh Realty Investors (FRI) appeals from the trial court’s decision, following a jury verdict, in this contract dispute. Landowner Robert Schumacher cross-appeals.[1] FRI argues that the court erred by: (1) denying its request to allow certain claims to go to the jury; (2) refusing to allow it to amend its complaint to add a new claim; (3) reducing the jury’s award of damages; and (4) denying its request for injunctive relief. Landowner asserts that the court erred in: (1) finding an enforceable contract; and (2) upholding the punitive damages award. With the exception of a revision to the jury award for breach of contract, we affirm

FRI sought to add an abuse of process claim to its complaint. FRI argues that its request should have been granted because it could have completed discovery on this claim prior to the rescheduled jury draw. The record shows that FRI sought to add this claim in April 2007, seven months after its original complaint was filed. The jury draw had already been continued once in March 2007.and the court again postponed the jury draw to August, The court did not err in refusing to postpone the proceedings further to accommodate FRI’s desire to add a new claim. See Colby v. Umbrella, Inc., 2008 VT 20, ¶ 4, 184 Vt. 1, 955 A.2d 1082 (denial of a motion under Rule 15(a) may be justified based upon a consideration of undue delay, among other factors). While FRI now suggests that it could have completed discovery on its new claim before the August jury draw, the court implicitly concluded otherwise. The trial court offered adequate grounds for its decision in this case, and we find no error.

We turn next to the punitive damages award. Schumacher argues that his conduct was not sufficiently egregious to warrant an award of such damages Schumacher fails to demonstrate that he preserved this argument. He did not raise the issue in his motion for a directed verdict at the close of FRI’s case, and he does not show that he raised the issue at trial. Instead, Schumacher appears to have raised the issue for the first time in his post-trial motion for judgment as a matter of law. He thus waived this claim of error. See V.R.C.P. 50(a), (b) (party who believes there is no legally sufficient evidentiary basis for reasonable jury to find for opposing party on certain issue must make motion for judgment as a matter of law before case is submitted to jury, and motion must be renewed post-verdict); Lemnah, 144 Vt. at 571, 482 A.2d at 702 (where defendant first challenged punitive damages by motion for judgment notwithstanding the verdict, issue was not preserved for review); see also V.R.A.P. 28(a)(4) (appellant’s brief should explain what the issues are, and how they were preserved).

SCOVT note. Compare Beaudoin v. Feldman2018 VT 83 (defendant  preserved his claim for appellate review by complying with V.R.C.P. 50(a) and (b), regardless of whether or not he also objected to the jury instruction on punitive damages.)